With the above-given information find the following ES of Task S…

Question With the above-given information find the following ES of Task S… Image transcription text2. Project ‘D’ data: Task Duration Predecessors $Budget Status at the end of (days) day 25 R 8 Start 5,000Completed and spent $5,000 S 3 R(FS+2) 3,000 Completed and spent $2,000 T 5 S(SS+10) 6,000 Half doneand spent $2,500 C 5 R, T(FF) 7,000 Not started and spent $100 E 4 C(SF+2) 4,000 80% done a… Show more… Show moreWith the above-given information find the following ES of Task S is??Es of task E is?The project duration is?BAC is?AC is?PV is?Ev is?CPI is? SPi is?EAC is?        Business Management Project Management PROJECT MANAGEMENT 5001 Share QuestionEmailCopy link Comments (0)